[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1102949,780,1,"单选题","根据《建筑法》，按国务院有关规定批准开工报告的建筑工程，因故不能按期开工超过（ ）个月的，应当重新办理开工报告的批准手续。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","12","考点:《建筑法》主要内容。根据《建筑法》第11条，按照国务院有关规定批准开工报告的建筑工程，因故不能按期开工或者中止施工的，应当及时向批准机关报告情况。因故不能按期开工超过6个月的，应当重新办理开工报告的批准手续。参见《建设工程监理相关法规文件汇编》P4。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]