[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1102889,780,1,"单选题","在正式验收前组织工程竣工预验收的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目监理机构",true,{"key":16,"text":17,"correct":18},"B","建设单位",false,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","建设行政主管部门","考点:建设工程监理实施程序和原则。建设工程施工完成后，项目监理机构应在正式验收前组织工程竣工预验收，在预验收中发现的问题，应及时与施工单位沟通，提出整改要求。项目监理机构人员应参加由建设单位组织的工程竣工验收，签署工程监理意见。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]