[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102883,780,1,"单选题","建设工程平行承包模式的缺点是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设周期较长",false,{"key":16,"text":17,"correct":18},"B","合同数量多",true,{"key":20,"text":21,"correct":14},"C","进度控制难度大",{"key":23,"text":24,"correct":14},"D","质量控制难度大","考点:建设工程监理委托方式。平行承包模式的缺点：合同数量多，会造成合同管理困难；工程造价控制难度大，表现为：一是工程总价不易确定，影响工程造价控制的实施；二是工程招标任务量大，需控制多项合同价格，增加了工程造价控制难度；三是在施工过程中设计变更和修改较多，导致工程造价增加。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]