[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1102864,780,1,"单选题","以建筑工程预制混凝土空心管桩分项工程为例，以下各项措施中，属于工程质量事中控制措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","要求施工单位在桩基平面布置图上对每根桩编号",false,{"key":16,"text":17,"correct":14},"B","施工现场准备情况检查",{"key":19,"text":20,"correct":21},"C","确定合理的压桩程序",true,{"key":23,"text":24,"correct":14},"D","施工单位确认自检合格后提出工程验收申请，由项目监理机构进行验收","考点:监理实施细则主要内容。事前控制措施是指为预防发生差错或问题而提前采取的措施；事中控制措施是指监理工作过程中，及时获取工程实际状况信息，以供及时发现问题、解决问题而采取的措施；事后控制措施是指发现工程相关指标与控制目标或标准之间出现差异后而采取的纠偏措施。选项AB属于工程质量事前控制措施；选项D属于工程质量事后控制措施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]