[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102827,780,1,"单选题","暂停施工事件发生时，（ ）应会同有关各方按施工合同约定，处理因工程暂停引起的与工期、费用有关的问题。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","总监理工程师代表",{"key":23,"text":24,"correct":14},"D","建设单位","考点:合同管理。暂停施工事件发生时，项目监理机构应如实记录所发生的情况。总监理工程师应会同有关各方按施工合同约定，处理因工程暂停引起的与工期、费用有关的问题。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]