[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1102826,780,1,"单选题","下列属于建设工程目标控制经济措施的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","明确各级目标控制人员的任务和职责分工",false,{"key":16,"text":17,"correct":14},"B","对多个不同的施工方案进行技术可行性分析",{"key":19,"text":20,"correct":14},"C","动态跟踪合同执行情况及处理好工程索赔等",{"key":22,"text":23,"correct":24},"D","投资偏差分析",true,"考点:目标控制。选项A属于三大目标控制的组织措施；选项B属于三大目标控制的技术措施；选项C属于三大目标控制的合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]