[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1102822,780,1,"单选题","下列反映建设工程三大目标之间对立关系的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","提高项目功能，能够减少运行费和维修费",false,{"key":16,"text":17,"correct":14},"B","缩短建设工期，能提早发挥投资效益",{"key":19,"text":20,"correct":14},"C","提高工程质量标准，能够节约工程项目动用后的运行费",{"key":22,"text":23,"correct":24},"D","减少工程投资，可能会降低项目功能",true,"考点:目标控制。在通常情况下，如果对工程质量有较高的要求，就需要投入较多的资金和花费较长的建设时间；如果要抢时间、争进度，以极短的时间完成建设工程，势必会增加投资或者使工程质量下降；如果要减少投资、节约费用，势必会考虑降低工程项目的功能要求和质量标准。这些表明，建设工程三大目标之间存在着矛盾和对立的一面。选项ABC反映三大目标之间的统一关系。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]