[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102815":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102815,780,1,"单选题","下列选项中，属于三大目标控制措施中合同措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调整控制人员的分工",false,{"key":16,"text":17,"correct":18},"B","动态跟踪合同执行情况及处理好工程索赔",true,{"key":20,"text":21,"correct":14},"C","要求施工单位增加施工机械，并给予合理的补偿",{"key":23,"text":24,"correct":14},"D","修改技术方案","考点:目标控制。加强合同管理是控制建设工程目标的重要措施。选择合理的承发包模式和合同计价方式，选定满意的施工单位及材料设备供应单位，拟订完善的合同条款，并动态跟踪合同执行情况及处理好工程索赔等，是控制建设工程目标的重要合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]