[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102813":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102813,780,1,"单选题","对于施工单位提出涉及工程设计文件修改的工程变更，必要时应召开工程设计文件修改方案的专题论证会议，该会议的正确组织方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由设计单位组织，建设.施工和监理单位参加",false,{"key":16,"text":17,"correct":18},"B","由建设单位组织，设计.施工和监理单位参加",true,{"key":20,"text":21,"correct":14},"C","由施工单位组织，建设.设计和监理单位参加",{"key":23,"text":24,"correct":14},"D","由监理单位组织，建设.设计和施工单位参加","考点:合同管理。对涉及工程设计文件修改的工程变更，应由建设单位转交原设计单位修改工程设计文件。必要时，项目监理机构应建议建设单位组织设计、施工等单位召开论证工程设计文件的修改方案的专题会议。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]