[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102812":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102812,780,1,"单选题","加强动态控制过程中的激励措施，调动和发挥员工实现建设工程目标的积极性和创造性，属于三大目标控制措施中的（ ）措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同",false,{"key":16,"text":17,"correct":18},"B","组织",true,{"key":20,"text":21,"correct":14},"C","技术",{"key":23,"text":24,"correct":14},"D","经济","考点:目标控制。组织措施包括：建立健全实施动态控制的组织机构、规章制度和人员，明确各级目标控制人员的任务和职责分工，改善建设工程目标控制的工作流程；建立建设工程目标控制工作考评机制，加强各单位（部门）之间的沟通协作；加强动态控制过程中的激励措施，调动和发挥员工实现建设工程目标的积极性和创造性等。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]