[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102811":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1102811,780,1,"单选题","建设工程目标动态控制过程中，实施工程项目计划之后需要做的工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","比较实施绩效和预定目标",false,{"key":16,"text":17,"correct":14},"B","分析偏差产生的原因",{"key":19,"text":20,"correct":21},"C","收集工程项目实施绩效",true,{"key":23,"text":24,"correct":14},"D","采取纠偏措施","考点:目标控制。建设工程项目动态控制过程：建设工程目标体系→编制工程项目计划→实施工程项目计划→收集工程项目实施绩效→比较实施绩效和预定目标→分析偏差产生的原因→采取纠偏措施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]