[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1102806,780,1,"单选题","对于列入城建档案管理部门接收档案的工程，负责移交工程档案资料的责任单位是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","建设单位",true,{"key":23,"text":24,"correct":14},"D","城建档案管理部门","考点:建设工程监理文件资料管理要求。列入城建档案管理部门接收范围的工程，建设单位在工程竣工验收后3个月内向城建档案管理部门移交一套符合规定的工程档案（监理文件资料）。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]