[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102801":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102801,780,1,"单选题","总监理工程师组织专业监理工程师审查施工单位报送的工程开工报审表及相关资料时，不属于审查内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计交底和图纸会审是否已完成",false,{"key":16,"text":17,"correct":18},"B","施工许可证是否已办理",true,{"key":20,"text":21,"correct":14},"C","施工单位质量管理体系是否已建立",{"key":23,"text":24,"correct":14},"D","施工组织设计是否已经过总监理工程审查签认","考点:建设工程监理基本表式及其应用说明。工程开工需审查的内容：（1）设计交底和图纸会审已完成；（2）施工组织设计已由总监理工程师签认；（3）施工单位现场质量、安全生产管理体系已建立，管理及施工人员已到位，施工机械具备使用条件，主要工程材料已落实；（4）进场道路及水、电、通信等已满足开工要求。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]