[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102798":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1102798,780,1,"单选题","工程质量评估报告应在（ ）提交给建设单位。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收前",true,{"key":16,"text":17,"correct":18},"B","竣工验收后",false,{"key":20,"text":21,"correct":18},"C","竣工预验收前",{"key":23,"text":24,"correct":18},"D","竣工验收备案后","考点:建设工程监理主要文件资料分类及编制要求。工程竣工预验收合格后，由总监理工程师组织专业监理工程师编制工程质量评估报告，编制完成后，由项目总监理工程师及监理单位技术负责人审核签认并加盖监理单位公章后报建设单位。工程质量评估报告应在正式竣工验收前提交给建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]