[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102791":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1102791,780,1,"单选题","施工单位申请工程延期时，项目监理机构对施工单位的申请事项进行审核并签署意见，由（ ）批准后方可延长合同工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","施工单位",false,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","建设主管部门","考点:建设工程监理基本表式及其应用说明。施工单位申请工程延期时，需要向项目监理机构报送《工程临时或最终延期报审表》。项目监理机构对施工单位的申请事项进行审核并签署意见，经建设单位批准后方可延长合同工期。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]