[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102778":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1102778,780,1,"单选题","评审工程设计成果需要进行的工作有：①邀请专家参与评审；②确定专家人选；③建立评审制度和程序；④收集专家评审意见；⑤分析专家评审意见。其正确的工作步骤是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①→②→④→③→⑤",false,{"key":16,"text":17,"correct":14},"B","①→③→②→④→⑤",{"key":19,"text":20,"correct":21},"C","③→②→①→④→⑤",true,{"key":23,"text":24,"correct":14},"D","②→①→④→③→⑤","考点:勘察设计阶段服务内容。工程设计成果评审程序如下：（1）事先建立评审制度和程序，并编制设计成果评审计划，列出预评审的设计成果清单；（2）根据设计成果特点，确定相应的专家人选；（3）邀请专家参与评审，并提供专家所需评审的设计成果资料、建设单位的需求及相关部门的规定等；（4）组织相关专家对设计成果评审会议，收集各专家的评审意见；（5）整理、分析专家评审意见，提出相关建议或解决方案，形成会议纪要或报告，作为设计优化或下一阶段设计的依据，并报建设单位或相关部门。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]