[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1102772,780,1,"单选题","某投标人在招标工程开标后发现自己由于报价失误，比正常报价少报25％，虽然被确定为中标人，但拒绝与业主签订施工合同，该风险对策为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风险回避",true,{"key":16,"text":17,"correct":18},"B","损失控制",false,{"key":20,"text":21,"correct":18},"C","风险自留",{"key":23,"text":24,"correct":18},"D","风险转移","考点:建设工程风险管理。风险回避是指在完成建设工程风险分析与评价后，如果发现风险发生的概率很高，而且可能的损失也很大，又没有其他有效的对策来降低风险时，应采取放弃项目、放弃原有计划或改变目标等方法，使其不发生或不再发展，从而避免可能产生的潜在损失。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]