[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1102768,780,1,"单选题","（ ）是指跟踪、检查和调整项目进展和绩效，识别必要的计划变更并启动相应变更的一组过程。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","启动过程组",false,{"key":16,"text":17,"correct":14},"B","计划过程组",{"key":19,"text":20,"correct":14},"C","执行过程组",{"key":22,"text":23,"correct":24},"D","监控过程组",true,"考点:PMBOK总体框架。监控过程组是指跟踪、检查和调整项目进展和绩效，识别必要的计划变更并启动相应变更的一组过程。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]