[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1102761,780,1,"单选题","关于建设工程风险的损失控制对策的说法中，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预防损失措施的主要作用在于遏制损失的发展",false,{"key":16,"text":17,"correct":14},"B","减少损失措施的主要作用在于降低损失发生的概率",{"key":19,"text":20,"correct":21},"C","制定损失控制措施必须考虑其付出的费用和时间方面的代价",true,{"key":23,"text":24,"correct":14},"D","损失控制的计划系统应由质量计划.进度计划和投资计划构成","考点:建设工程风险管理。选项AB错误，预防损失措施的主要作用在于降低或消除（通常只能做到降低）损失发生的概率，而减少损失措施的作用在于降低损失的严重性或遏制损失的进一步发展，使损失最小化。选项D错误，损失控制计划系统一般应由预防计划、灾难计划和应急计划三部分组成。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]