[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102758,780,1,"单选题","风险事件K、L、M、N发生的概率分别为PK=5％、PL=8％、PM=12％、PN=15％，相应的损失后果分别为QK=30万元、QL=15万元、QM=10万元、QN=5万元，则风险量相等的风险事件为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","K和M",false,{"key":16,"text":17,"correct":18},"B","L和M",true,{"key":20,"text":21,"correct":14},"C","M和N",{"key":23,"text":24,"correct":14},"D","K和N","考点:建设工程风险管理。15×8%=12%×10。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]