[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102749":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1102749,780,1,"单选题","Project Controlling与Partnering模式的共同之处是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","信息共享",false,{"key":16,"text":17,"correct":18},"B","不能独立存在",true,{"key":20,"text":21,"correct":14},"C","长期协议",{"key":23,"text":24,"correct":14},"D","协调机制","考点:Partnering模式。这两种模式均不能独立存在，往往与建设工程组织管理模式中的多种模式同时共存。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]