[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-779-32":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":728},{"id":5,"name":6,"category":7,"favorite":8},779,"合同管理","建筑工程",0,32,50,2250,[13,38,53,68,83,98,112,126,140,155,170,185,200,214,229,243,258,272,285,299,314,329,344,359,373,387,400,414,428,442,456,470,484,497,511,526,540,554,568,581,595,610,619,633,647,658,671,685,699,714],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},1101860,2,"多选题","在施工安全管理中，安全事故处理程序包括()。",[19,23,26,30,33],{"key":20,"text":21,"correct":22},"A","通知",true,{"key":24,"text":25,"correct":22},"B","及时采取减损措施",{"key":27,"text":28,"correct":29},"C","停工",false,{"key":31,"text":32,"correct":22},"D","报告",{"key":34,"text":35,"correct":29},"E","复工","ABD","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},1101861,"按照《建设工程施工合同》的规定，“合同工期”包括()。",[42,44,46,48,50],{"key":20,"text":43,"correct":22},"承包人在投标函内承诺完成合同工程的时间期限",{"key":24,"text":45,"correct":22},"按照合同条款通过变更应给予顺延工期的时间",{"key":27,"text":47,"correct":29},"承包商原因导致的工期顺延",{"key":31,"text":49,"correct":22},"不可抗力导致的工期顺延",{"key":34,"text":51,"correct":22},"发包商原因导致的工期顺延","ABDE",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":67,"analysis":37},1101862,"根据标准，施工招标文件的施工合同文本，通用合同条款可以同时给承包人工期，费用和利润补偿的情形( )",[57,59,61,63,65],{"key":20,"text":58,"correct":22},"监理人的指示延误",{"key":24,"text":60,"correct":29},"发包人提供的材料和工程设备提前交货",{"key":27,"text":62,"correct":29},"异常恶劣的气候条件",{"key":31,"text":64,"correct":29},"法规变化引起的价格调整",{"key":34,"text":66,"correct":22},"隐蔽工程重新检验质量合格","AE",{"id":69,"libraryId":5,"type":15,"typeLabel":16,"stem":70,"options":71,"answer":82,"analysis":37},1101863,"施工合同中，属于发包人义务的是（）",[72,74,76,78,80],{"key":20,"text":73,"correct":29},"提出开工申请",{"key":24,"text":75,"correct":29},"编制施工实施计划",{"key":27,"text":77,"correct":29},"编制施工环保措施计划",{"key":31,"text":79,"correct":22},"提供现场外的道路通行权",{"key":34,"text":81,"correct":22},"提供地下管线和地下设施的相关资料","DE",{"id":84,"libraryId":5,"type":15,"typeLabel":16,"stem":85,"options":86,"answer":97,"analysis":37},1101864,"施工合同中，监理人职责中关于开工通知，说法正确的是（）",[87,89,91,93,95],{"key":20,"text":88,"correct":22},"当发包人的开工前期工作已完成且临近约定的开工日期时，应委托监理人接专用条款约定的时间向承包人发出开工通知",{"key":24,"text":90,"correct":29},"如果约定的开工已届至但发包人应完成的开工配合义务尚未完成(如现场移交延误)，由于监理人不能按时发出开工通知，则合同工期不予顺延",{"key":27,"text":92,"correct":22},"如果发包人开工前的配合工作已完成且约定的开工日期已届至，但承包人的开工准备还不满足开工条件，监理人仍应按时发出开工的指示，合同工期不予顺延。",{"key":31,"text":94,"correct":22},"监理人征得发包人同意后，应在开工日期7天前向承包人发出开工通知",{"key":34,"text":96,"correct":29},"监理工程师发出开工通知后，合同工期自合同规定的开工日起计算","ACD",{"id":99,"libraryId":5,"type":15,"typeLabel":16,"stem":100,"options":101,"answer":111,"analysis":37},1101865,"标准施工合同中，可以给承包人补偿利润的情况有（）",[102,104,106,107,109],{"key":20,"text":103,"correct":29},"施工现场发现文物、化石",{"key":24,"text":105,"correct":29},"施工现场出现不利物质条件",{"key":27,"text":58,"correct":22},{"key":31,"text":108,"correct":29},"发包人提供的材料提前交货",{"key":34,"text":110,"correct":22},"因发包人原因导致的暂停施工","CE",{"id":113,"libraryId":5,"type":15,"typeLabel":16,"stem":114,"options":115,"answer":82,"analysis":37},1101866,"在施工阶段，下列关于工程款支付管理说法错误的有()。",[116,118,120,122,124],{"key":20,"text":117,"correct":29},"因非承包人原因导致工期顺延，原定竣工日后的支付过程中，调价公式继续有效",{"key":24,"text":119,"correct":29},"索赔金额属于在通用条款中要求进度付款申请单的内容",{"key":27,"text":121,"correct":29},"质量保证金是用于因施工原因修复缺陷工程的开支项目",{"key":31,"text":123,"correct":22},"因承包人原因未在约定工期内竣工，后续支付要按照原约定竣工日价格指数",{"key":34,"text":125,"correct":22},"通用条款规定，监理人出具的进度付款证书，应视为监理人已同意承包人完成的工作",{"id":127,"libraryId":5,"type":15,"typeLabel":16,"stem":128,"options":129,"answer":82,"analysis":37},1101867,"根据《标准施工合同》，下列不属于承包人的施工安全责任有（ ）。",[130,132,134,136,138],{"key":20,"text":131,"correct":29},"编制施工安全措施计划",{"key":24,"text":133,"correct":29},"严格按国家安全标准制定施工安全操作规程",{"key":27,"text":135,"correct":29},"配备必要的安全生产和劳动保护措施",{"key":31,"text":137,"correct":22},"赔偿施工现场所有人员工伤事故损失",{"key":34,"text":139,"correct":22},"赔偿工程对土地占有所造成的第三者财产损失",{"id":141,"libraryId":5,"type":15,"typeLabel":16,"stem":142,"options":143,"answer":154,"analysis":37},1101868,"标准施工合同签订合同时签约合同价内尚不确定的款项包括（ ）。",[144,146,148,150,152],{"key":20,"text":145,"correct":22},"暂估价",{"key":24,"text":147,"correct":22},"暂列金额",{"key":27,"text":149,"correct":22},"费用和利润",{"key":31,"text":151,"correct":29},"签约合同价",{"key":34,"text":153,"correct":22},"质量保证金","ABCE",{"id":156,"libraryId":5,"type":15,"typeLabel":16,"stem":157,"options":158,"answer":169,"analysis":37},1101869,"通用条款中要求施工阶段进度付款申请单的内容包括（ ）。",[159,161,163,165,167],{"key":20,"text":160,"correct":22},"变更金额",{"key":24,"text":162,"correct":22},"索赔金额",{"key":27,"text":164,"correct":22},"本次扣减的质量保证金",{"key":31,"text":166,"correct":22},"本次应支付的预付款和扣减的返还预付款",{"key":34,"text":168,"correct":29},"截至本次付款周期末未实施工程的价款","ABCD",{"id":171,"libraryId":5,"type":15,"typeLabel":16,"stem":172,"options":173,"answer":184,"analysis":37},1101870,"(2009年真题)下列在施工过程发生的事件中，可以顺延工期的情况包括（ ）。",[174,176,178,180,182],{"key":20,"text":175,"correct":22},"不可抗力事件的影响",{"key":24,"text":177,"correct":29},"承包人采购的施工材料未按时交货",{"key":27,"text":179,"correct":22},"施工许可证没有及时颁发",{"key":31,"text":181,"correct":22},"发包人不具备合同约定的开工条件",{"key":34,"text":183,"correct":22},"工程师未按合同约定提供所需指令","ACDE",{"id":186,"libraryId":5,"type":15,"typeLabel":16,"stem":187,"options":188,"answer":199,"analysis":37},1101871,"(2010年真题)导致现场发生暂停施工的下列情形中，承包商在执行工程师暂停施工的指示后，可以要求发包人追加合同价款并顺延工期的包括（ ）。",[189,191,193,195,197],{"key":20,"text":190,"correct":29},"施工作业方法可能危及邻近建筑物的安全",{"key":24,"text":192,"correct":22},"施工中遇到了有考古价值的文物",{"key":27,"text":194,"correct":22},"发包人订购的设备不能按时到货",{"key":31,"text":196,"correct":29},"施工作业危及人身安全",{"key":34,"text":198,"correct":22},"发包人未能按时移交后续施工的现场","BCE",{"id":201,"libraryId":5,"type":15,"typeLabel":16,"stem":202,"options":203,"answer":52,"analysis":37},1101872,"(2011年真题)工程师依据施工现场的下列情况向承包人发布暂停施工指令时，其中应顺延合同工期的情况有（ ）。",[204,206,208,210,212],{"key":20,"text":205,"correct":22},"地基开挖遇到勘察资料未标明的断层，需要重新确定基础处理方案",{"key":24,"text":207,"correct":22},"发包人订购的设备未能按时到货",{"key":27,"text":209,"correct":29},"施工作业方法存在重大安全隐患",{"key":31,"text":211,"correct":22},"后续施工现场未能按时完成移民拆迁工作",{"key":34,"text":213,"correct":22},"施工中遇到有考古价值的文物需要采取保护措施予以保护",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":228,"analysis":37},1101873,"(2014年真题)根据《标准施工合同》，关于监理人的地位和职责的说法，正确的有（ ）。",[218,220,222,224,226],{"key":20,"text":219,"correct":22},"监理人是受发包人聘请的合同履行管理人",{"key":24,"text":221,"correct":29},"监理人是施工合同履行中独立的第三方",{"key":27,"text":223,"correct":22},"监理人在授权范围内独立开展工作",{"key":31,"text":225,"correct":29},"监理人具有施工合同管理所有事项的决定权",{"key":34,"text":227,"correct":22},"监理人有对承包人进行施工管理的指示权","ACE",{"id":230,"libraryId":5,"type":15,"typeLabel":16,"stem":231,"options":232,"answer":52,"analysis":37},1101874,"(2014年真题)根据《标准施工合同》，暂列金额的主要特点有（ ）。",[233,235,237,239,241],{"key":20,"text":234,"correct":22},"用于支付签订协议书时尚未确定的工程设备款",{"key":24,"text":236,"correct":22},"用于支付签订协议书时不可预见的变更费用",{"key":27,"text":238,"correct":29},"不能用于计日工支付",{"key":31,"text":240,"correct":22},"属于签约合同价的一部分",{"key":34,"text":242,"correct":22},"承包人不一定能全部获得约定的暂列金额",{"id":244,"libraryId":5,"type":15,"typeLabel":16,"stem":245,"options":246,"answer":257,"analysis":37},1101875,"(2014年真题)根据《标准施工招标文件》，标准施工合同附件的格式文件包括（ ）。",[247,249,251,253,255],{"key":20,"text":248,"correct":22},"合同协议书",{"key":24,"text":250,"correct":29},"通用条款",{"key":27,"text":252,"correct":29},"专用条款",{"key":31,"text":254,"correct":22},"履约保函",{"key":34,"text":256,"correct":22},"预付款保函","ADE",{"id":259,"libraryId":5,"type":15,"typeLabel":16,"stem":260,"options":261,"answer":97,"analysis":37},1101876,"(2015年真题)根据《标准施工合同》，保险的正确处理方式有（ ）。",[262,264,266,268,270],{"key":20,"text":263,"correct":22},"发承包双方应分别为自己在现场所有人员投保人身意外伤害险",{"key":24,"text":265,"correct":29},"发包人应以自己的名义投保工程设备险",{"key":27,"text":267,"correct":22},"承包人应以自己的名义投保施工设备险",{"key":31,"text":269,"correct":22},"发包人应为履行合同的本方人员缴纳工伤保险费",{"key":34,"text":271,"correct":29},"承包人应以自己的名义投保进场材料险",{"id":273,"libraryId":5,"type":15,"typeLabel":16,"stem":274,"options":275,"answer":52,"analysis":37},1101877,"(2015年真题)根据《标准施工合同》，合同协议书中需要明确填写的内容有（ ）。",[276,277,279,281,283],{"key":20,"text":151,"correct":22},{"key":24,"text":278,"correct":22},"合同工期",{"key":27,"text":280,"correct":29},"双方义务",{"key":31,"text":282,"correct":22},"质量标准",{"key":34,"text":284,"correct":22},"项目经理人选",{"id":286,"libraryId":5,"type":15,"typeLabel":16,"stem":287,"options":288,"answer":298,"analysis":37},1101878,"(2016年真题)根据《标准施工合同》，合同协议书中需要明确填写的内容有（ ）。",[289,291,293,294,296],{"key":20,"text":290,"correct":22},"施工工程或标段",{"key":24,"text":292,"correct":29},"工程结算方式",{"key":27,"text":282,"correct":22},{"key":31,"text":295,"correct":29},"合同组成文件",{"key":34,"text":297,"correct":29},"变更处理程序","AC",{"id":300,"libraryId":5,"type":15,"typeLabel":16,"stem":301,"options":302,"answer":313,"analysis":37},1101879,"(2016年真题)根据《标准施工合同》，如果承包人有专利技术且有相应设计资质，双方约定由承包人完成部分工程施工图设计时，需要在订立合同时明确的内容有（ ）",[303,305,307,309,311],{"key":20,"text":304,"correct":29},"发包人提交施工图审查的时间",{"key":24,"text":306,"correct":22},"承包人的设计范围",{"key":27,"text":308,"correct":22},"承包人提交设计文件的期限",{"key":31,"text":310,"correct":22},"承包人提交设计文件的数量",{"key":34,"text":312,"correct":22},"监理人签发图纸修改的期限","BCDE",{"id":315,"libraryId":5,"type":15,"typeLabel":16,"stem":316,"options":317,"answer":328,"analysis":37},1101880,"(2016年真题)关于施工进度管理中，承包人原因延误的说法中，不正确的是（ ）。",[318,320,322,324,326],{"key":20,"text":319,"correct":29},"未能按合同进度计划完成工作时，承包人应采取措施加快进度，并承担加快进度所增加的费用",{"key":24,"text":321,"correct":22},"由于发包人原因造成工期延误，承包人应支付逾期竣工违约金",{"key":27,"text":323,"correct":29},"订立合同时，应在专用条款内约定逾期竣工违约金的计算方法和逾期违约金的最高限额",{"key":31,"text":325,"correct":29},"专用条款说明中建议，违约金计算方法约定的日拖期赔偿额，可采用每天为多少钱或每天为签约合同价的千分之几",{"key":34,"text":327,"correct":22},"专用条款说明中建议，最高赔偿限额为签约合同价的8%","BE",{"id":330,"libraryId":5,"type":15,"typeLabel":16,"stem":331,"options":332,"answer":343,"analysis":37},1101881,"(2017年真题)关于工程保险和第三者责任保险办理责任的说法中，正确的有（ ）。",[333,335,337,339,341],{"key":20,"text":334,"correct":22},"《标准施工合同》要求在专用条款具体约定保险金不足以赔偿损失时，承包人和发包人应承担的责任",{"key":24,"text":336,"correct":22},"如果投保工程一切险的保险金额少于工程实际价值，工程受到保险事件的损害时，不能从保险公司获得实际损失的全额赔偿，则损失赔偿的不足部分按合同相应条款的约定，由该事件的风险责任方负责补偿",{"key":27,"text":338,"correct":22},"保险人做出保险责任变动的，承包人应在收到保险人通知后立即通知发包人和监理人",{"key":31,"text":340,"correct":29},"承包人需要变动保险合同条款时，应直接通知监理人即可，无需经过发包人同意",{"key":34,"text":342,"correct":29},"《标准施工合同》和《简明施工合同》的通用条款中均规定由发包人负责投保“建筑工程一切险”、“安装工程一切险”和“第三者责任保险”，并承担办理保险的费用","ABC",{"id":345,"libraryId":5,"type":15,"typeLabel":16,"stem":346,"options":347,"answer":358,"analysis":37},1101882,"(2017年真题)关于建设工程施工合同中，物价浮动合同价格调整的说法，正确的有（ ）。",[348,350,352,354,356],{"key":20,"text":349,"correct":22},"通用条款规定的基准日期指投标截止日前第28天",{"key":24,"text":351,"correct":22},"承包人以基准日期前的市场价格编制工程报价，长期合同中调价公式中的可调因素价格指数来源于基准日的价格",{"key":27,"text":353,"correct":29},"合同履行期间市场价格浮动对施工成本造成的影响是否允许调整合同价格，要视合同成本高低来决定.",{"key":31,"text":355,"correct":29},"适用于工期在12个月以内的《简明施工合同》的通用条款应设有调价条款",{"key":34,"text":357,"correct":22},"工期12个月以上的施工合同，由于承包人在投标阶段不可能合理预测一年以后的市场价格变化，因此应设有调价条款，由发包人和承包人共同分担市场价格变化的风险","ABE",{"id":360,"libraryId":5,"type":15,"typeLabel":16,"stem":361,"options":362,"answer":228,"analysis":37},1101883,"(2017年真题)关于施工合同履行中缺陷责任期的说法，正确的有（ ）。",[363,365,367,369,371],{"key":20,"text":364,"correct":22},"缺陷责任期从工程接收证书中写明的竣工日开始起算",{"key":24,"text":366,"correct":29},"缺陷责任期限视具体工程的性质和使用条件的不同在专用条款内约定（一般为2年）",{"key":27,"text":368,"correct":22},"由于承包人拥有施工技术、设备和施工经验，缺陷责任期内工程运行期间出现的工程缺陷，承包人应负责修复，直到检验合格为止",{"key":31,"text":370,"correct":29},"承包人责任原因产生的较大缺陷或损坏，致使工程不能按原定目标使用，经修复后需要再行检验或试验时，发包人即不得再要求延长该部分工程或设备的缺陷责任期",{"key":34,"text":372,"correct":22},"影响工程正常运行的有缺陷工程或部位，在修复检验合格日前已经过的时间归于无效，重新计算缺陷责任期，但包括延长时间在内的缺陷责任期最长时间不得超过2年",{"id":374,"libraryId":5,"type":15,"typeLabel":16,"stem":375,"options":376,"answer":386,"analysis":37},1101884,"(2017年真题)施工准备阶段发包人的义务包括（ ）。",[377,379,380,382,384],{"key":20,"text":378,"correct":29},"现场查勘",{"key":24,"text":73,"correct":29},{"key":27,"text":381,"correct":22},"提供施工场地",{"key":31,"text":383,"correct":22},"组织设计交底",{"key":34,"text":385,"correct":22},"约定开工时间","CDE",{"id":388,"libraryId":5,"type":15,"typeLabel":16,"stem":389,"options":390,"answer":399,"analysis":37},1101885,"(2018年真题)根据《标准施工合同》，发包人在施工准备阶段的主要义务有（ ）。",[391,393,394,396,397],{"key":20,"text":392,"correct":29},"审定施工方案",{"key":24,"text":383,"correct":22},{"key":27,"text":395,"correct":22},"提供施工现场",{"key":31,"text":385,"correct":22},{"key":34,"text":398,"correct":29},"讨论通过施工组织设计","BCD",{"id":401,"libraryId":5,"type":15,"typeLabel":16,"stem":402,"options":403,"answer":328,"analysis":37},1101886,"(2018年真题)根据《标准施工合同》，关于监理人地位的说法，正确的有（ ）。",[404,406,408,410,412],{"key":20,"text":405,"correct":29},"监理人是受发包人委托的发包人代表",{"key":24,"text":407,"correct":22},"监理人是受发包人聘请的管理人",{"key":27,"text":409,"correct":29},"监理人属于施工合同履行管理的独立第三方",{"key":31,"text":411,"correct":29},"监理人属于遵守发包人指示的发包人一方人员",{"key":34,"text":413,"correct":22},"监理人是受发包人委托对合同履行实施管理的法人或其他组织",{"id":415,"libraryId":5,"type":15,"typeLabel":16,"stem":416,"options":417,"answer":399,"analysis":37},1101887,"(2018年真题)根据《标准施工招标资格预审文件和标准施工招标文件试运行规定》，各行业编制本行业标准施工合同应遵守的原则有（ ）。",[418,420,422,424,426],{"key":20,"text":419,"correct":29},"结合行业特点，编制本行业的通用合同条款",{"key":24,"text":421,"correct":22},"不加修改地引用标准文件中的“通用合同条款”",{"key":27,"text":423,"correct":22},"结合施工项目的具体特点，编制“专用合同条款”",{"key":31,"text":425,"correct":22},"“专用合同条款”补充和细化的内容不得与“通用合同条款”相抵触",{"key":34,"text":427,"correct":29},"“通用合同条款”不能约定“专用合同条款”可以修改“通用合同条款”",{"id":429,"libraryId":5,"type":15,"typeLabel":16,"stem":430,"options":431,"answer":399,"analysis":37},1101888,"(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，“暂估价”和“暂列金额”的主要区别有（ ）。",[432,434,436,438,440],{"key":20,"text":433,"correct":29},"是否列入已标价的工程量清单",{"key":24,"text":435,"correct":22},"是否在招标阶段已经确定价格",{"key":27,"text":437,"correct":22},"是否在合同履行阶段必然发生",{"key":31,"text":439,"correct":22},"承包人是否必然获得支付",{"key":34,"text":441,"correct":29},"是否包括在签约合同价内",{"id":443,"libraryId":5,"type":15,"typeLabel":16,"stem":444,"options":445,"answer":52,"analysis":37},1101889,"(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，采取不足额投保方式的，当发生保 险事件时，对于损失赔偿不足的部分，采取的处理原则有（ ）。",[446,448,450,452,454],{"key":20,"text":447,"correct":22},"不足的部分按合同相应条款约定，由该事件的风险责任方负责赔偿",{"key":24,"text":449,"correct":22},"保险公司按实际损失的相应比例予以赔偿",{"key":27,"text":451,"correct":29},"不足的部分由发包人全部承担",{"key":31,"text":453,"correct":22},"永久工程损失的差额由发包人补偿",{"key":34,"text":455,"correct":22},"临时工程和施工设备等损失由承包人补偿",{"id":457,"libraryId":5,"type":15,"typeLabel":16,"stem":458,"options":459,"answer":358,"analysis":37},1101890,"(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，监理人的主要职责有（ ）。",[460,462,464,466,468],{"key":20,"text":461,"correct":22},"独立处理单价的合同调整的索赔批准",{"key":24,"text":463,"correct":22},"在发包人授权范围内，负责发出指示、检查施工质量、控制进度等现场管理工作",{"key":27,"text":465,"correct":29},"依据工程实际情况作出指示，免除或变更承包人的部分义务",{"key":31,"text":467,"correct":29},"决定发包人与承包人有关合同争议的处理",{"key":34,"text":469,"correct":22},"按照合同约定，公平合理地处理合同履行过程中涉及的有关事项",{"id":471,"libraryId":5,"type":15,"typeLabel":16,"stem":472,"options":473,"answer":36,"analysis":37},1101891,"(2019年真题)关于《标准施工招标文件》的施工合同文本通用合同条款规定的“基准日期”的说法，正确的有（ ）。",[474,476,478,480,482],{"key":20,"text":475,"correct":22},"承包人以基准日期前的市场价格编制工程报价",{"key":24,"text":477,"correct":22},"长期合同中调价公式中的可调因素价格指数以基准日的价格为准",{"key":27,"text":479,"correct":29},"承包人以基准日期后的市场价格编制工程报价",{"key":31,"text":481,"correct":22},"基准日期后，因法律政策、规范标准的变化，导致承包人工程成本发生约定以外的增减，相应调整合同价款",{"key":34,"text":483,"correct":29},"基准日期即为投标截止日",{"id":485,"libraryId":5,"type":15,"typeLabel":16,"stem":486,"options":487,"answer":399,"analysis":37},1101892,"(2019年真题)据《标准施工招标文件》的施工合同文本通用，合同条款，承包人按合同约定完成的主要工作有（ ）。",[488,490,492,494,495],{"key":20,"text":489,"correct":29},"组织设计人、监理人进行施工图纸和设计文件的交底",{"key":24,"text":491,"correct":22},"核对工程资料，进一步收集相关的地质、水文等资料",{"key":27,"text":493,"correct":22},"编制施工组织设计和施工进度计划",{"key":31,"text":77,"correct":22},{"key":34,"text":496,"correct":29},"准备施工用的测量基准点、基准线和水准点等书面资料",{"id":498,"libraryId":5,"type":15,"typeLabel":16,"stem":499,"options":500,"answer":343,"analysis":37},1101893,"(2016年真题)如投保工程一切险的保险金额少于工程实际价值，工程因保险事件损害时正确做法（ ）。",[501,503,505,507,509],{"key":20,"text":502,"correct":22},"保险公司按投保的保险金额所占百分比赔偿实际损失",{"key":24,"text":504,"correct":22},"损失赔偿的不足部分由保险事件的风险责任方负责补偿",{"key":27,"text":506,"correct":22},"永久工程损失赔偿的不足部分由发包人承担",{"key":31,"text":508,"correct":29},"已完工工程损失由承包人承担",{"key":34,"text":510,"correct":29},"施工设备和进场材料损失由保险公司承担",{"id":512,"libraryId":5,"type":15,"typeLabel":16,"stem":513,"options":514,"answer":525,"analysis":37},1101894,"(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，承包人竣工清场的主要义务有（ ）。",[515,517,519,521,523],{"key":20,"text":516,"correct":29},"就交付工程的使用功能向发包人交接",{"key":24,"text":518,"correct":22},"拆除临时工程，清理，平整或复原场地",{"key":27,"text":520,"correct":29},"保证工程建筑物周边及其附近道路交通通畅",{"key":31,"text":522,"correct":22},"施工场地内承包人设备和剩余材料已按计划撤离现场",{"key":34,"text":524,"correct":22},"施工场地内残留垃圾已全部清除出场","BDE",{"id":527,"libraryId":5,"type":15,"typeLabel":16,"stem":528,"options":529,"answer":36,"analysis":37},1101895,"(2015年真题)根据《标准施工合同》，关于暂估价的说法，正确的有（ ）。",[530,532,534,536,538],{"key":20,"text":531,"correct":22},"暂估价中涉及的专业工程一定会实施",{"key":24,"text":533,"correct":22},"暂估价是签约合同价的组成部分",{"key":27,"text":535,"correct":29},"暂估价中涉及的专业工程不需要进行招标",{"key":31,"text":537,"correct":22},"暂估价金额需要在合同履行阶段最终确定",{"key":34,"text":539,"correct":29},"暂估价金额由监理人控制使用",{"id":541,"libraryId":5,"type":15,"typeLabel":16,"stem":542,"options":543,"answer":199,"analysis":37},1101896,"(2015年真题)根据《标准施工合同》，工程施工合同订立阶段承包人应履行的义务有（ ）。",[544,546,548,550,552],{"key":20,"text":545,"correct":29},"收集地下管线资料",{"key":24,"text":547,"correct":22},"编制施工组织设计",{"key":27,"text":549,"correct":22},"测设施工控制网",{"key":31,"text":551,"correct":29},"组织施工图设计交底",{"key":34,"text":553,"correct":22},"提交工程开工报审表",{"id":555,"libraryId":5,"type":15,"typeLabel":16,"stem":556,"options":557,"answer":36,"analysis":37},1101897,"(2017年真题)根据《标准施工合同》，关于工程计量的说法，正确的有（ ）。",[558,560,562,564,566],{"key":20,"text":559,"correct":22},"单价子目已完工程量按月计量",{"key":24,"text":561,"correct":22},"总价子目的计量支付不考虑市场价格浮动",{"key":27,"text":563,"correct":29},"总价子目巳完工程量按月计量",{"key":31,"text":565,"correct":22},"总价子目表中标明的工程量通常不进行现场计量",{"key":34,"text":567,"correct":29},"总价子目表中标明的工程量通常不进行图纸计量",{"id":569,"libraryId":5,"type":15,"typeLabel":16,"stem":570,"options":571,"answer":199,"analysis":37},1101898,"(2010年真题)根据标准施工合同通用条款的规定，下列情形中，可以给予承包商延长合同工期的有（ ）。",[572,574,576,578,579],{"key":20,"text":573,"correct":29},"物价浮动引起的价格调整",{"key":24,"text":575,"correct":22},"施工遇到不可预见的不利于施工的外界条件",{"key":27,"text":577,"correct":22},"业主提前占用部分工程导致后续施工的延误",{"key":31,"text":64,"correct":29},{"key":34,"text":580,"correct":22},"施工中受到其他承包商的干扰",{"id":582,"libraryId":5,"type":15,"typeLabel":16,"stem":583,"options":584,"answer":169,"analysis":37},1101899,"(2018)根据《标准施工合同》，属于发包人原因可以延长合同工期的情形有（ ）",[585,587,589,591,593],{"key":20,"text":586,"correct":22},"增加工作内容",{"key":24,"text":588,"correct":22},"提供图纸延误",{"key":27,"text":590,"correct":22},"出现异常恶劣的气候条件",{"key":31,"text":592,"correct":22},"发包人延迟提供建筑材料",{"key":34,"text":594,"correct":29},"现场查勘滞后",{"id":596,"libraryId":5,"type":15,"typeLabel":16,"stem":597,"options":598,"answer":609,"analysis":37},1101900,"(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，规定因不可抗力造成的损失，由发包人承担的有（ ）。",[599,601,603,605,607],{"key":20,"text":600,"correct":22},"永久工程的损失",{"key":24,"text":602,"correct":29},"施工设备损坏",{"key":27,"text":604,"correct":29},"停工损失",{"key":31,"text":606,"correct":22},"施工场地的材料和工程设备",{"key":34,"text":608,"correct":29},"承包人的人员伤亡损失","AD",{"id":611,"libraryId":5,"type":15,"typeLabel":16,"stem":612,"options":613,"answer":67,"analysis":37},1101901,"(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，可以同时给承包人工期、费用和利润补偿的情形有（ ）。",[614,615,616,617,618],{"key":20,"text":58,"correct":22},{"key":24,"text":60,"correct":29},{"key":27,"text":62,"correct":29},{"key":31,"text":64,"correct":29},{"key":34,"text":66,"correct":22},{"id":620,"libraryId":5,"type":15,"typeLabel":16,"stem":621,"options":622,"answer":184,"analysis":37},1101902,"(2015年真题)根据《标准施工合同》，关于单位工程验收的说法，正确的有（ ）。",[623,625,627,629,631],{"key":20,"text":624,"correct":22},"移交后的单位工程由发包人负责照管",{"key":24,"text":626,"correct":29},"所有单位工程均在工程竣工时一并验收",{"key":27,"text":628,"correct":22},"单位工程验收应由发包人组织",{"key":31,"text":630,"correct":22},"单位工程验收成果和结论应作为全部工程竣工验收申请报告的附件",{"key":34,"text":632,"correct":22},"单位工程验收合格后，应由监理人出具经发包人签认的单位工程验收证书",{"id":634,"libraryId":5,"type":15,"typeLabel":16,"stem":635,"options":636,"answer":199,"analysis":37},1101903,"(2016年真题)根据《标准施工合同》，关于签约合同价的说法，正确的有（ ）。",[637,639,641,643,645],{"key":20,"text":638,"correct":29},"签约合同价不包括承包人利润",{"key":24,"text":640,"correct":22},"签约合同价即为中标价",{"key":27,"text":642,"correct":22},"签约合同价包含暂列金额、暂估价",{"key":31,"text":644,"correct":29},"签约合同价是承包方履行合同义务后应得的全部工程价款",{"key":34,"text":646,"correct":22},"签约合同价应在合同协议书中写明",{"id":648,"libraryId":5,"type":15,"typeLabel":16,"stem":649,"options":650,"answer":399,"analysis":37},1101904,"(2015年真题)根据《标准施工合同》，承包人的施工安全责任有（ ）。",[651,653,654,656,657],{"key":20,"text":652,"correct":29},"赔偿工程对土地占用所造成的第三者财产损失",{"key":24,"text":131,"correct":22},{"key":27,"text":655,"correct":22},"制定施工安全操作规程",{"key":31,"text":135,"correct":22},{"key":34,"text":137,"correct":29},{"id":659,"libraryId":5,"type":15,"typeLabel":16,"stem":660,"options":661,"answer":399,"analysis":37},1101905,"(2016年真题)根据《标准施工合同》，工程施工中承包人有权获得费用补偿和工期延期，并获得合理利润的情形有（ ）。",[662,664,666,668,669],{"key":20,"text":663,"correct":29},"发现文物、化石等的处理",{"key":24,"text":665,"correct":22},"发包人改变合同中任何一项工作的质量要求",{"key":27,"text":667,"correct":22},"发包人未按合同约定及时支付工程进度款导致暂停施工",{"key":31,"text":66,"correct":22},{"key":34,"text":670,"correct":29},"不可抗力事件发生后的清理工作",{"id":672,"libraryId":5,"type":15,"typeLabel":16,"stem":673,"options":674,"answer":399,"analysis":37},1101906,"(2014年真题)根据《标准施工合同》，履约担保和预付款担保的主要区别有（ ）。",[675,677,679,681,683],{"key":20,"text":676,"correct":29},"担保的方式不同",{"key":24,"text":678,"correct":22},"担保的金额不同",{"key":27,"text":680,"correct":22},"担保的期限不同",{"key":31,"text":682,"correct":22},"担保的作用不同",{"key":34,"text":684,"correct":29},"被担保的主体不同",{"id":686,"libraryId":5,"type":15,"typeLabel":16,"stem":687,"options":688,"answer":358,"analysis":37},1101907,"（2013年真题）按照施工合同内不可抗力条款的规定，下列事件中属于不可抗力的有（ ）。",[689,691,693,695,697],{"key":20,"text":690,"correct":22},"龙卷风导致吊车倒塌",{"key":24,"text":692,"correct":22},"地震导致主体建筑物的开裂",{"key":27,"text":694,"correct":29},"承包人管理不善导致的仓库爆炸",{"key":31,"text":696,"correct":29},"承包人拖欠雇员工资导致的动乱",{"key":34,"text":698,"correct":22},"非发包人和承包人责任发生的火灾",{"id":700,"libraryId":5,"type":15,"typeLabel":16,"stem":701,"options":702,"answer":713,"analysis":37},1101908,"（2020年真题）根据《标准施工招标文件》中的通用合同条款，关于预付款担保金额的说法，正确的有（ ） ．",[703,705,707,709,711],{"key":20,"text":704,"correct":22},"承包人提交的担保金额应与收到的合同约定的预付款金额保持一致",{"key":24,"text":706,"correct":22},"发包人从工程进度款中已扣除部分预付款后，担保金额可相应递减",{"key":27,"text":708,"correct":29},"担保金额在发包人未扣除全部预付款前应高于合同约定的预付款金额",{"key":31,"text":710,"correct":29},"担保金额不应低于预付款金额减去已向承包人签发的进度款支付证书中扣除的金额",{"key":34,"text":712,"correct":29},"担保金额必须保持与剩余预付款额相同","AB",{"id":715,"libraryId":5,"type":15,"typeLabel":16,"stem":716,"options":717,"answer":298,"analysis":37},1101909,"（2020年真题）根据《标准施工招标文件》中的通用合同条款，关于监理人指示的说法，正确的有（ ）。",[718,720,722,724,726],{"key":20,"text":719,"correct":22},"监理人指示错误给承包人造成的损失应由发包人承担赔偿责任",{"key":24,"text":721,"correct":29},"监理人根据工程情况变化可以指示免除承包人的部分合同责任",{"key":27,"text":723,"correct":22},"监理人未按合同约定发出的指示延误导致承包人增加的施工成本应由发包人承担",{"key":31,"text":725,"correct":29},"监理人根据工程设计变更指示可以改变承包人的有关合同义务",{"key":34,"text":727,"correct":29},"监理人对承包人施工进度计划变更的批准应视为免除承包人工期延误的责任",[729,733,736,739,742,745],{"id":730,"name":731,"category":7,"favorite":732},1,"领导干部任职前廉政法规知识测试题",92,{"id":734,"name":735,"category":7,"favorite":730},595,"建筑结构与设备",{"id":737,"name":738,"category":7,"favorite":730},715,"招标采购专业知识与法律法规",{"id":740,"name":741,"category":7,"favorite":730},848,"市政方向-通用基础",{"id":743,"name":744,"category":7,"favorite":8},534,"BIM工程师",{"id":746,"name":744,"category":7,"favorite":8},535]