[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102694":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102694,779,2,"多选题","保险公司对“建筑工程一切险”开始承担保险责任的日期，应是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业主提供场地日",false,{"key":16,"text":17,"correct":14},"B","承包商提交履约人保函日",{"key":19,"text":20,"correct":21},"C","保险工程在工地动工",true,{"key":23,"text":24,"correct":21},"D","承保项目所用材料卸至工地日",{"key":26,"text":27,"correct":14},"E","投保工程投保日","CD","知识点:工程建设涉及的主要险种。建筑工程一切险的保险责任自保险工程在工地动工或用于保险工程的材料、设备运抵工地之时起始。2020版教材P20。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]