[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102670":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102670,779,2,"多选题","根据AIA合同的规定，（ ）情况可以与雇主协商调整保证工程最大费用（GMP）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发生设计变更或补充图纸",true,{"key":16,"text":17,"correct":14},"B","业主要求变更材料、设备的标准、系统、种类、数量和质量",{"key":19,"text":20,"correct":14},"C","业主签约交由CM承包商管理的施工承包商或雇主指定分包商与CM承包商签约的合同价大于GMP中的相应金额",{"key":22,"text":23,"correct":24},"D","工期延误超过21天",false,{"key":26,"text":27,"correct":24},"E","承包商工程机械更新","ABC","知识点:美国AIA合同文本。选项D和E不属于情况的内容。可能的情况包括：发生设计变更或补充图纸；业主要求变更材料和设备的标准、种类、数量和质量；业主签约交由CM承包商管理的施工承包商或业主指定分包商与CM承包商签约的合同价大于GMP中的相应金额等。2020版教材P166。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]