[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102667":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102667,779,2,"多选题","IPD合同中，将整个项目实施过程分为8个阶段，以下属于项目划分阶段的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","概念阶段",true,{"key":16,"text":17,"correct":14},"B","采购分包阶段",{"key":19,"text":20,"correct":21},"C","准备阶段",false,{"key":23,"text":24,"correct":14},"D","施工阶段",{"key":26,"text":27,"correct":14},"E","机构审查阶段","ABDE","知识点:IPD的8个阶段。概念阶段；标准设计阶段；详细设计阶段；执行文件阶段；机构审查阶段；采购分包阶段；施工阶段；竣工收尾阶段。2020版教材P166。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]