[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102663":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102663,779,2,"多选题","根据ECC合同，以下有关早期警告的论述，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目经理可要求对方出席早期警告会议",true,{"key":16,"text":17,"correct":14},"B","承包商可要求对方出席早期警告会议",{"key":19,"text":20,"correct":21},"C","项目经理和承包商任何一方都可在邀请其他人员出席该会议",false,{"key":23,"text":24,"correct":14},"D","在早期警告会上寻求对将要受影响的所有各方均有利的解决办法",{"key":26,"text":27,"correct":21},"E","工程师应在早期警告会议上对所研究的建议和做出的决定记录在案，并将记录发给业主和承包商","ABD","知识点:ECC合同中的合作伙伴管理理念。选项C，项目经理和承包商都可要求对方出席早期警告会议，每一方都可在对方同意后要求其他人员出席该会议；选项E，项目经理应在早期警告会议上对所研究的建议和做出的决定记录在案，并将记录发给承包商。2020版教材P163",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]