[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102661":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102661,779,2,"多选题","在FIDIC设计采购施工EPC合同条件中，以下（ ）承包商有权提出要求延长竣工时间的索赔。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","异常不利的气候条件",false,{"key":16,"text":17,"correct":18},"B","发生合同变更导致工期延长",true,{"key":20,"text":21,"correct":18},"C","业主造成的延误或阻碍",{"key":23,"text":24,"correct":18},"D","业主的其他承包商造成的延误或阻碍",{"key":26,"text":27,"correct":14},"E","由于流行病或政府行为导致的不可预见的人员或货物的短缺","BCD","知识点:《设计采购施工（EPC）\u002F交钥匙合同条件》工期索赔的情形。异常不利的气候条件以及由于流行病或政府行为导致的不可预见的人员或货物的短缺这两种情况不能索赔工期。2020版教材P161。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]