[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102658":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102658,779,2,"多选题","根据FIDIC施工合同条件，以下有关不可预见的物质条件论述正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","包括承包商在工程实施中遇见的外界自然条件及人为的条件",true,{"key":16,"text":17,"correct":14},"B","包括承包商在工程实施中遇见的其他障碍和污染物",{"key":19,"text":20,"correct":21},"C","不包括地下和水文条件",false,{"key":23,"text":24,"correct":14},"D","不包括气侯条件",{"key":26,"text":27,"correct":21},"E","承包商有权提出工期和费用和利润索赔","ABD","本题考查《FIDIC施工合同条件》中不可预见的物质条件的内涵。选项C，包括地下和水文条件。选项E，承包商有权提出工期和费用索赔，但不包括利润。 2020版教材P155。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]