[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102655":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102655,779,2,"多选题","根据FIDIC施工合同条件，项目通过了试验或颁发了证书后，工程师可以指示进行的工作包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","进行项目日常管理工作",false,{"key":16,"text":17,"correct":14},"B","进行工程结算",{"key":19,"text":20,"correct":21},"C","对不符合合同规定的任何工作进行返工",true,{"key":23,"text":24,"correct":21},"D","将不符合合同规定的永久设备或材料从现场移走并进行更换",{"key":26,"text":27,"correct":21},"E","实施任何因事故、不可预见事件等导致的为保护工程安全而急需的工作","CDE","本题考查《FIDIC施工合同条件》中规定。通过了试验或颁发了证书后，工程师可以指示的修补工作包括（1）将不符合合同规定的永久设备或材料从现场移走并进行更换 （2）对不符合合同规定的任何工作进行返工。（3）实施任何因事故、不可预见事件等导致的为保护工程安全而急需的工作。2020版教材P154。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]