[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102653":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102653,779,2,"多选题","设计施工总承包模式下，材料和工程设备费，一般按（ ）阶段按比例进行分解支付。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","订立采购合同",true,{"key":16,"text":17,"correct":18},"B","设备制造完成",false,{"key":20,"text":21,"correct":14},"C","进场验收合格",{"key":23,"text":24,"correct":14},"D","安装就位",{"key":26,"text":27,"correct":14},"E","工程竣工","ACDE","知识点:工程款支付管理。设备制造完成不作为支付节点。2020版教材P130。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]