[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102643":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102643,779,2,"多选题","根据《标准设计施工总承包合同》，承包人建议书应包括的内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程设计方案",true,{"key":16,"text":17,"correct":18},"B","工程施工方案",false,{"key":20,"text":21,"correct":14},"C","工程分包方案",{"key":23,"text":24,"correct":18},"D","工程报价清单",{"key":26,"text":27,"correct":14},"E","工程设备方案","ACE","知识点:设计施工总承包合同合同文件。承包人建议书是对“发包人要求”的响应文件，包括承包人的工程设计方案和设备方案的说明；分包方案；对发包人要求中的错误说明等内容。合同谈判阶段，随着发包人要求的调整，承包人建议书也应对一些技术细节进一步予以明确或补充修改，作为合同文件的组成部分。2020版教材P123。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]