[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102641":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102641,779,2,"多选题","设计施工总承包合同模式下，发包人的职责包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对工程项目的实施负责投资支付",true,{"key":16,"text":17,"correct":14},"B","对项目建设有关重大事项的决定",{"key":19,"text":20,"correct":21},"C","负责试运行的质量缺陷修复责任",false,{"key":23,"text":24,"correct":21},"D","负责缺陷责任期的质量缺陷修复",{"key":26,"text":27,"correct":21},"E","提供图纸及采购设备","AB","知识点:设计施工总承包合同管理有关各方的职责。发包人负责投资及重大事项的决策。2020版教材P120。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]