[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102636":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102636,779,2,"多选题","在设备招标的综合评估法评标中，以下说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","每个评标委员会成员对评价因素响应值的评价结果称为独立评价值",true,{"key":16,"text":17,"correct":18},"B","评价值为各独立评价值之和",false,{"key":20,"text":21,"correct":18},"C","最差的评价因素得基准评价值，其余的评价因素将依据其优劣程度获得相应的评价值",{"key":23,"text":24,"correct":14},"D","若投标人的投标价格超出最高投标限价，其投标将被否决",{"key":26,"text":27,"correct":14},"E","综合评价最高者为排名第一的中标候选人","ADE","知识点:材料设备采购的三种方式。选项B，评价值=评标委员会成员的有效独立评价值之和\u002F有效评委数 。选项C，最优的评价因素得基准评价值，其余的评价因素将依据其优劣程度获得相应的评价值。2020版教材P72。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]