[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102630":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102630,779,2,"多选题","材料设备采购招标中，以下说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料设备招标的基本单位是标包",true,{"key":16,"text":17,"correct":18},"B","标包划分得越细越好",false,{"key":20,"text":21,"correct":18},"C","投标人只能投一个标包，不能同时投多个标包",{"key":23,"text":24,"correct":14},"D","标包划分过大，中小供应厂商无法满足供应",{"key":26,"text":27,"correct":14},"E","标包划分过小，缺乏对大型供应厂商的吸引力","ADE","知识点:材料设备采购招标特点。选项B，标包过大或过小均不合适。选项C，投标人可投一个或几个标包，但不能投一个标包中的某几项。2020版教材P63。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]