[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102625":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102625,779,2,"多选题","《标准设计施工总承包招标文件》中的发包人要求附件清单，包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","性能保证表",true,{"key":16,"text":17,"correct":14},"B","工作界区图",{"key":19,"text":20,"correct":14},"C","工程项目管理规定",{"key":22,"text":23,"correct":14},"D","竣工后试验规定",{"key":25,"text":26,"correct":27},"E","竣工图纸编制",false,"ABCD","知识点:标准设计施工总承包招标文件中，发包人要求附件清单的组成。没有竣工图编制这一项。2020版教材P61。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]