[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102619":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102619,779,2,"多选题","根据《标准资格预审文件》的规定，以下（ ）属于初步审查标准。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","申请函的签字盖章",true,{"key":16,"text":17,"correct":14},"B","申请文件的格式",{"key":19,"text":20,"correct":14},"C","投标保函",{"key":22,"text":23,"correct":24},"D","业绩",false,{"key":26,"text":27,"correct":24},"E","项目经理资格","ABC","知识点:申请人须知。初步审查主要审查资料的有效性和完整性。选项DE属于详细审查标准。2020版教材P52。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]