[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102614":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102614,779,2,"多选题","组织投标人踏勘现场的时间一般应在（ ）之前进行。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投标预备会召开15日之前",false,{"key":16,"text":17,"correct":18},"B","投标预备会召开之前",true,{"key":20,"text":21,"correct":14},"C","投标人资格预审之前",{"key":23,"text":24,"correct":14},"D","发售招标文件之前",{"key":26,"text":27,"correct":18},"E","投标截止时间15日之前","BE","知识点:现场踏勘的时间要求。组织投标人踏勘现场的时间一般应在投标截止时间15日前及投标预备会召开前进行。2020版教材P43。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]