[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102609":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102609,779,2,"多选题","根据《标准施工招标文件》的规定，（ ）情况，可以不再招标。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","重新招标后投标人仍少于3个",true,{"key":16,"text":17,"correct":14},"B","重新招标后所有投标被否决",{"key":19,"text":20,"correct":21},"C","发包方认为可以不招标的",false,{"key":23,"text":24,"correct":21},"D","未提交投标保证金的",{"key":26,"text":27,"correct":21},"E","未提交履约保证金的","AB","知识点:评标、决标阶段的工作。重新投标后，投标人仍少于3家或所有投标人又全部被否决，属于必须审批或核准的工程建设项目，经原审批或批准部门批准后不再进行招标，采用直接发包的形式委托施工单位完成建设任务。2020版教材P45。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]