[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102599":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102599,779,2,"多选题","合同履行发生的下列费用中，可纳入承包人提交的工程进度款支付申请书中的款项包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","截至提交日已实施工程的价款",false,{"key":16,"text":17,"correct":18},"B","变更金额",true,{"key":20,"text":21,"correct":18},"C","本次应支付的预付款和扣减的返还预付款",{"key":23,"text":24,"correct":18},"D","本期扣减的质量保证金",{"key":26,"text":27,"correct":18},"E","承包人的索赔款","BCDE","知识点:工程款支付管理。选项A，应是截止本次付款周期末已实施工程的价款，不是截止申请之日已实施工程的价款。通用条款中要求进度付款申请单的内容包括：（1）截至本次付款周期末已实施工程的价款；（2） 变更金额；（3）索赔金额；（4）本次应支付的预付款和扣减的返还预付款；（5）本次扣减的质量保证金；（6）根据合同应增加和扣减的其他金额。2020版教材P107。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]