[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102598":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102598,779,2,"多选题","下列在施工阶段发生的事件中，可以顺延工期的情况包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不可抗力事件的影响",true,{"key":16,"text":17,"correct":14},"B","发包人采购的施工材料未按时交货",{"key":19,"text":20,"correct":21},"C","施工机械发生故障导致停工",false,{"key":23,"text":24,"correct":14},"D","图纸错误引起的停工待图",{"key":26,"text":27,"correct":14},"E","工程师未按合同约定提供所需指令","ABDE","知识点:索赔管理。非承包人原因造成的延误，可以顺延工期。2020版教材P100",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]