[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102597":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102597,779,2,"多选题","承包人请求竣工验收时，应满足的条件有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人的施工已完成合同范围内的全部单位工程以及有关工作",false,{"key":16,"text":17,"correct":18},"B","已按合同约定的内容和份数备齐了符合要求的竣工资料",true,{"key":20,"text":21,"correct":18},"C","已按监理人的要求编制了在缺陷责任期内完成的尾工（甩项）工程和缺陷修补工作清单以及相应施工计划",{"key":23,"text":24,"correct":18},"D","监理人要求在竣工验收前应完成的其他工作",{"key":26,"text":27,"correct":18},"E","监理人要求提交的竣工验收资料清单","BCDE","知识点:竣工验收管理。选项A，允许甩项验收。2020版教材P115。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]