[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102595":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102595,779,2,"多选题","根据《施工合同标准文本》规定，导致现场发生暂停施工的下列情形中，承包商可以要求发包人补偿费用并顺延工期的包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","基准资料有误引起的损失及拖延",true,{"key":16,"text":17,"correct":14},"B","隐蔽工程重新检验质量合格",{"key":19,"text":20,"correct":21},"C","发包人订购的设备提前交货",false,{"key":23,"text":24,"correct":21},"D","法规变化引起的价格调整",{"key":26,"text":27,"correct":21},"E","不可抗力不能按期竣工","AB","知识点:索赔管理。选项CD，不可顺延工期；选项E，不可抗力不可获得费用补偿。2020版教材P111。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]