[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102592":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102592,779,2,"多选题","根据《标准施工合同》，暂列金额的主要特点有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","用于支付签订协议书时尚未确定的工程设备款",true,{"key":16,"text":17,"correct":14},"B","用于支付签订协议书时不可预见的变更费用",{"key":19,"text":20,"correct":21},"C","不能用于计日工支付",false,{"key":23,"text":24,"correct":21},"D","不属于签约合同价的一部分",{"key":26,"text":27,"correct":14},"E","承包人不一定能全部获得约定的暂列金额","ABE","知识点:工程款支付管理。暂列金额指已标价工程量清单中所列的一笔款项，用于在签订协议书时尚未确定或不可预见变更的施工及其所需材料、工程设备、服务等的金额，包括以计日工方式支付的款项。签约合同价内约定的暂列金额可能全部使用或部分使用，因此承包人不一定能够全部获得支付。2020版教材P104。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]