[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102590":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102590,779,2,"多选题","按照《施工合同标准文本》通用条款的规定，因不可抗力事件导致的损失应由发包人承担的包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程本身的损害",true,{"key":16,"text":17,"correct":14},"B","由发包人采购，已运至施工现场待安装设备的损害",{"key":19,"text":20,"correct":14},"C","由承包人采购，已运至施工现场待安装设备的损害",{"key":22,"text":23,"correct":24},"D","承包方人员伤亡",false,{"key":26,"text":27,"correct":24},"E","承包人停工损失","ABC","知识点:不可抗力。不可抗力发生后，发包方与承包方需承担的损失分别如下表所示。2020版教材P110。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]