[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102589":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102589,779,2,"多选题","根据《标准施工合同》，投标文件中的部分内容在订立合同后允许进行修改或调整，如施工前应编制更为详尽的（ ） 。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","签约合同价",false,{"key":16,"text":17,"correct":18},"B","施工组织设计",true,{"key":20,"text":21,"correct":14},"C","合同工期",{"key":23,"text":24,"correct":14},"D","履约担保",{"key":26,"text":27,"correct":18},"E","施工进度计划","BE","知识点:合同文件。投标文件中的部分内容在订立合同后允许进行修改或调整，如施工前应编制更为详尽的施工组织设计、进度计划等。2020版教材P93。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]