[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102580":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102580,779,2,"多选题","根据九部委发布的标准设计合同，以下有关设计审查的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人接收设计文件之后，应当组织专家会进行审查",false,{"key":16,"text":17,"correct":18},"B","发包人对于设计文件的审查期限，自文件接收之日起不应超过14天",true,{"key":20,"text":21,"correct":14},"C","发包人逾期未做出审查结论，视为设计未通过发包人审查",{"key":23,"text":24,"correct":14},"D","发包人审查后不同意设计文件的，设计人承担违约责任",{"key":26,"text":27,"correct":18},"E","修改设计方案后重新进行审查的，审查期限重新起算","BE","知识点:设计合同中设计文件的审查的规定。选项A，发包人可以自行审查，也可以组织专家审查。选项C，发包人逾期未作结论的，视为设计已通过审查。选项D，发包人审查后不同意设计文件的，设计人应根据发包人的审查意见修改完善设计文件，并重新报送发包人审查。而不是直接视为设计人违约。2020版教材P86。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]