[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102578":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102578,779,2,"多选题","根据九部委发布的《标准设计合同》，以下属于勘察人违约的情形是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","勘察人转包、违法分包或者未经发包人同意擅自分包",true,{"key":16,"text":17,"correct":18},"B","发包人提供的基础资料有错误",false,{"key":20,"text":21,"correct":14},"C","勘察人未按合同计划完成勘察，从而造成工程损失",{"key":23,"text":24,"correct":14},"D","勘察人无法履行或停止履行合同",{"key":26,"text":27,"correct":18},"E","未按时支付勘察费","ACD","知识点:勘察合同违约。选项BE为发包人违约。2020版教材P82。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]