[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102511":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102511,779,2,"多选题","（2020年真题）建设工程合同相关各方编制的合同实施计划应包括的内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同文体比选",false,{"key":16,"text":17,"correct":18},"B","合同实施总体安排",true,{"key":20,"text":21,"correct":18},"C","合同分解与管理策划",{"key":23,"text":24,"correct":18},"D","合同实施保证体系的建立",{"key":26,"text":27,"correct":14},"E","合同索赔结果分析","BCD","P3-6 合同签订及履行阶段的管理任务和方法。合同实施计划是保证合同履行的重要手段，合同相关各方应根据合同编制合同实施计划。合同实施计划应包括：（1）合同实施总体安排，（2） 合同分解与管理策划，（3） 合同实施保证体系的建立。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]