[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102443":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102443,779,2,"多选题","建筑工程一切险自保险工程在工地动工或用于保险工程的材料、设备运抵工地时生效，其保险期终止时间可以是（）日。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程动工",false,{"key":16,"text":17,"correct":18},"B","全部工程验收合格",true,{"key":20,"text":21,"correct":18},"C","工程所有人实际占有全部工程",{"key":23,"text":24,"correct":14},"D","施工合同约定的竣工",{"key":26,"text":27,"correct":14},"E","保修期满","BC","2020版教材P20 本题考查的是建筑工程一切险，建筑工程一切险自保险工程在工地动工或用于保险工程的材料、设备运抵工地时生效，至工程签发工程验收证书或验收合格，或工程所有人实际占用或使用或接受该部分或全部工程时终止，以先发生者为准。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]