[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102413":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102413,779,2,"多选题","发包人的下列行为中，造成建设工程质量缺陷，应当承担过错责任的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","提供的设计有缺陷",true,{"key":16,"text":17,"correct":14},"B","提供的建筑材料不符合强制性标准",{"key":19,"text":20,"correct":21},"C","同意总承包人选择分包人分包专业工程",false,{"key":23,"text":24,"correct":14},"D","指定购买的建筑构配件不符合强制性标准",{"key":26,"text":27,"correct":14},"E","直接指定分包人分包专业工程","ABDE","本题考查的是竣工质量争议的规定。选项C是发包人的合法权利。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]